Using the information provided in the table, the network diagram and the project completion time = 25 weeks, reduce the completion time of the project by 5 weeks in the most economical way.

Activity

Normal Time
(weeks)

Normal
Cost ($)

Crash Time
(weeks)

Crash
Cost ($)

Maximum
Weeks
Reduced

Crash Cost
per Week ($)

A

3 550 2 930 1 380

B

4 650 3 740 1 90

C

6 800 3 1,310 3 170

D

6 1,500 4 2,140 2 320

E

6 1,750 4 2,250 2 250

F

5 200 5 200 0 0

G

7 1,400 5 1,690 2 145

H

3 500 3 500 0 0

AON network diagram

(If there is no amount for a box enter 0. All boxes must be filled.)

Reduce A by ____________a number of weeks week(s), B by ———- a number of weeks week(s), C by ————— a number of weeks week(s), D by —————-a number of weeks week(s), E by ————— a number of weeks week(s), F by —————– a number of weeks week(s), G by ———— a number of weeks week(s), H by ————- a number of weeks week(s).
Total additional cost is $enter total additional cost in dollars
 

 

Leave a Comment

Your email address will not be published. Required fields are marked *

GradeEssays.com
We are GradeEssays.com, the best college essay writing service. We offer educational and research assistance to assist our customers in managing their academic work. At GradeEssays.com, we promise quality and 100% original essays written from scratch.
Contact Us

Enjoy 24/7 customer support for any queries or concerns you have.

Phone: +1 213 3772458

Email: support@gradeessays.com

© 2020 -2025 GradeEssays.com. All rights reserved.

WE HAVE A GIFT FOR YOU!

15% OFF 🎁

Get 15% OFF on your order with us

Scroll to Top