Use the Work Breakdown Structure, PDM, Scope of Work, and

Use the Work Breakdown Structure, PDM, Scope of Work, and Budget to identify PROJECT RISKS using a risk register showing description, P/I, and responses using the template below.

Risk Register

Scope of Work (SOW)

1. Animal exhibits will include giraffes, elephants, penguins, polar bears, flamingoes, sea-lions, zebras and a rare snow fox.

2. The giraffes will co-exist with the elephants as will the flamingoes and sea-lions.

3. Each exhibit must be designed to reflect the natural habitat of the species.

4. All exhibits must be incorporated into the high-level park layout which needs to be created.

5. Hire and train following staff:

– Specialized veterinarian and support personnel must be trained and hired for each species.

– Zoo veterinarians must have ACZM certification.

– General grounds crew for maintenance consisting of landscapers and construction crews.

– Guest services group which includes security, ticket sales and special events.

6. Create three concession stands with different wildlife themes of which one will serve beer and wine.

7. Create two gift shops at each end of the park.

8. Partner with the community and offer day camps during the summer for underprivileged children including facilities such as Transportation, Breakfast, Lunch and an approved curriculum from the WWF.

Project Schedule/ Work Break Down Structure

Budget

According to the information in the exercise, The Activity on node is listed below. As Project Manager we must continue keeping the project ahead of schedule and under budget.

The Expected time of the project is 150 days. The critical path of the project contains all activities with slack equal to zero. Then, the critical path is Task 1.01- Task 1.02- Task 1.04 – Task 1.05 – Task 1.06 – Task 1.07 – Task 1.10.

  • BAC = 121,000
  • AC = 6,250
  • PV = 5,045.70
  • EV = 24,200
  • SV = 19,154.30; the project is ahead of schedule.
  • CV = 17,950; the project is under budget.
  • SPI = 4.7962; the project is ahead of schedule.
  • CPI = 3.872; the project is under budget.

a) Budget at Completion (BAC)

  • BAC = 15,000 + 7,500 + 30,000 + 15,000 + 500 + 50,000 + 3,000
  • BAC = 121,000

b) Actual Costs (AC)

  • AC = 6,250

c) Planned Value (PV)

  • PV = (% expected work completed) x BAC
  • The rate per hour of the Wildlife Architect is: 125
  • The Wildlife Architect was paid: 6,250

DIAGRAM METHOD (PDM)

 

 

Leave a Comment

Your email address will not be published. Required fields are marked *

GradeEssays.com
We are GradeEssays.com, the best college essay writing service. We offer educational and research assistance to assist our customers in managing their academic work. At GradeEssays.com, we promise quality and 100% original essays written from scratch.
Contact Us

Enjoy 24/7 customer support for any queries or concerns you have.

Phone: +1 213 3772458

Email: support@gradeessays.com

© 2024 - GradeEssays.com. All rights reserved.

WE HAVE A GIFT FOR YOU!

15% OFF 🎁

Get 15% OFF on your order with us

Scroll to Top