Interest rate | Present value of an annuity of $1 factor for year 5 |
10% | 3.7908 |
12% | 3.6048 |
14% |
3.4331 |
Calculate the internal rate of return to determine whether it should accept this project.
The project should be accepted because it will earn more than 14%.
The project should be accepted because it will earn more than 10%.
The project will earn more than 12% but less than 14%. At a hurdle rate of 14%, the project should be rejected.
The project should be rejected because it will earn less than 14%.
The project should be rejected because it will not earn exactly 14%.