On September 1 2001 ABC co. enters into a contract

On September 1 2001 ABC co. enters into a contract with a customerto remodel a plants electrical wiring and install a new generator for a total consideration of 12 million. 30 modeling and installation are treated as single performance obligation satisfied overtime read.
The expected contract cost are as follows:
Generator                                            4 million
Other cost                                            5 million
Expected total contract cost              9million
Additional information:
●       ABC Co. uses the cost to cost method in measuring its progress towards the complete satisfaction of the performance of the obligation.
●       ABC Corporation incurs total cost of 6 million in 20×1, including the cost of generator.
●       Customer obtains control of the generator when it is delivered to the site in December 2001. However, the generator will not be installed until March 20×2.
●       ABC Corporation regards the cost of the generator as significant in relation to the expected total contracts cost. (I.e. 4M÷9M= 44.44%)
●       Although ABC Co. acted as a principal in procuring the generator, ABC co. that involve designing or manufacturing generator.
 
 -How much revenue is recognized in 2001?
 -How much profit is recognize from the contract in 2001?Conrado Motors sells locally manufactured Jeepney on the installment basis.
The information presented below related operation during the past 3 years.
                                                                               2012                   2011                 2010
Cost of installment sales.                              8,765,000.       7,700,000        4,950,000
December 31 balance:
Installment receivable 2012                          9,728,000
Installment receivable 2011                          3,025,000.        8,387,500
Installment 2010                                            1,512,500.          4,812,500
Gross profit rate.                                                32%.                 40%.                 28%
Conrado uses installment method of accounting. What would the company report as total realized gross profit of the year 2012?
a.      1,012,000
b.      3,044,250
c.       3,753,750
d.      6,993,250
. In 2015 ACE BUILDERS agreed to construct a commercial building at a price of 3,750,000 ACE BUILDERS uses the percentage of completion method. The information relating to the cost and buildings for the contract were as follows:
                                                                                               2015                      2016                         2017
Cost incurred to date                                         1,050,000                             2,250,000             2,943,750
Estimated cost yet to be incurred                 1,950,000                750,000
Customers billings to date                                              562,500                               1,500,000               3,750,000
Collections of billings to date                           450,000                             1,200,000            3,525,000
How much is the excess of the construction in progress over progress billings or progress billings over construction in progress in ACE’s December 31, 2016 balance sheet?
a.      1,312,500
b.      2,062,500
c.       Answer not given

 

Stressed over that homework?

Essay deadline breathing down your neck?

Let’s cut to the chase: Why struggle when you can ace it with zero hassle?

Whether it’s essays, research papers, or assignments — we’ve got you covered.

✅ Expert writers
✅ 100% original work
✅ No AI tools, just real pros

Stressed about your essay or homework? Get a top-quality custom essay NOW!!! Stop worrying. Start succeeding.

GradeEssays.com
We are GradeEssays.com, the best college essay writing service. We offer educational and research assistance to assist our customers in managing their academic work. At GradeEssays.com, we promise quality and 100% original essays written from scratch.
Contact Us

Enjoy 24/7 customer support for any queries or concerns you have.

Phone: +1 213 3772458

Email: support@gradeessays.com

© 2024 - GradeEssays.com. All rights reserved.

WE HAVE A GIFT FOR YOU!

15% OFF 🎁

Get 15% OFF on your order with us

Scroll to Top