Goal programming is a very useful technique for decision making in the complex task of formulating a public-sector investment program, given the existence of multiple objectives. Quantitative targets need to be set to provide objective measures of the potential of each investment program towards the attainment of the nation’s development objectives. The goal program then seeks to minimize the effect of the inevitable deviations from the desired target levels of attainment.

The following table provides information regarding 14 projects under consideration with estimates of capital costs (CC) in $million, construction duration (CD) in months, present value of net benefits (NPV) in $mil, employment during construction (WN) in man years, new permanent jobs created for operation on completion (JC), power consumption (PR) in mw, water consumption (W) in mil. Gallons and natural gas consumption (NG) in mil. ft3/day.

Define the decision variables as xj = 1 if project I is chosen, 0 otherwise
The following are goals:
1. The goal is to have the total NPV ≥ 1050 as much as possible.
2. Projects 8, 9, and 13 are infrastructure projects. The goal is to complete as many of these as far as is possible.
3. Projects 1, 7 and 10 are unfinished projects at the start of the plan period. 

The amount of completion at the beginning of this funding cycle are: .2, .3, .1, respectively. This goal is to complete each of these outstanding projects as far as possible.
4. The budget available for capital costs is 3500. It is desired to have the total capital costs be ≤ this budget as much as possible and cannot exceed 3750 overall (This is a hard constraint).
5. Total jobs needed by the construction is desired to be 20,000 person-years or greater as far as is possible. Total employment generated by construction is not allowed to go below 15,000 (This is a hard constraint).
6. Number of new jobs created after selected projects are completed are desire to be ≥ 6000 as far as possible.
7. In order to utilize the natural resource base, it is desired to have Natural Gas exceed 350 as far as possible.
8. It is desired to invest in at least two foreign exchange earnings projects other than petrochemicals (these are projects 2, 4, 5, 6, 11 and 12) as far as possible.
9. There is a desire to keep the sum of the fractional investments in the two projects 5 and 11 of the high-risk category ≤ 1, as far as possible.
10. There is a desire to keep the power consumption for the selected projects to be ≤400 as far as possible.
11. There is a desire to keep the water consumption for the selected projects to be ≤9.0 as far as possible.

QUESTION A. Formulate this goal-programming problem for determining the optimal x vector in this problem by taking the weights for deviations from the goals 1 through 11 to be 10, 10, 10, 8, 8, 8, 6, 6, 6, 4, 4. For this part, please provide an algebraic formulation that a technical manager can read and understand. In this part of the project, the variables are allowed to be fractional, that is, your xi variables are allowed to take on values between zero and one.

 

Stressed over that homework?

Essay deadline breathing down your neck?

Let’s cut to the chase: Why struggle when you can ace it with zero hassle?

Whether it’s essays, research papers, or assignments — we’ve got you covered.

✅ Expert writers
✅ 100% original work
✅ No AI tools, just real pros

Stressed about your essay or homework? Get a top-quality custom essay NOW!!! Stop worrying. Start succeeding.

GradeEssays.com
We are GradeEssays.com, the best college essay writing service. We offer educational and research assistance to assist our customers in managing their academic work. At GradeEssays.com, we promise quality and 100% original essays written from scratch.
Contact Us

Enjoy 24/7 customer support for any queries or concerns you have.

Phone: +1 213 3772458

Email: support@gradeessays.com

© 2024 - GradeEssays.com. All rights reserved.

WE HAVE A GIFT FOR YOU!

15% OFF 🎁

Get 15% OFF on your order with us

Scroll to Top