Given the following information, draw the project network

  1. Given the following information, draw the project network diagram compute the ,early , late and slake time for each activity. Identify the critical path (CP) 
  2. Use PERT to analyze the chance the delays on CP activities does not push the project duration beyond 40 days. 
ID
Optimistic
Most likely
Pessimistic
Predecessor
A 2 4 6 None
B 10 11 12 A
C 5 6 9 A
D 2 8 8 A
E 5 6 15 B,C
F 2 2 2 D
G 3 5 7 E,F
H 7 7 17 F
I 3 6 8 G,H

 

Leave a Comment

Your email address will not be published. Required fields are marked *

GradeEssays.com
We are GradeEssays.com, the best college essay writing service. We offer educational and research assistance to assist our customers in managing their academic work. At GradeEssays.com, we promise quality and 100% original essays written from scratch.
Contact Us

Enjoy 24/7 customer support for any queries or concerns you have.

Phone: +1 213 3772458

Email: support@gradeessays.com

© 2024 - GradeEssays.com. All rights reserved.

WE HAVE A GIFT FOR YOU!

15% OFF 🎁

Get 15% OFF on your order with us

Scroll to Top