Draw the AON and use the Critical path method to compute the CP, and total slack.
- Use PERT to analyze the chance the delays on CP activities does not push the project duration beyond 35 days.
x: is a last digit of your roll number
y: is a # of sibilings (0,1…….)
z: is a last digit of your mobile number
Activity | predecessors |
Optimistic | Most likely | Pessimistic |
A | – | 5 | 6 | 8 |
B | – | 3 | 4 | 5 |
C | A | 2 | 3 | 4 |
D | B | x-1 | x +4 | x+2 |
E | B | 1 | 3 | 4 |
F | – | 8 | 10 -z | 15-z |
G | E,F | 2 | 3 | 4 |
H | C,D | 2+x | 2+y | 2+z |