Using the information provided in the table, the network diagram and the project completion time = 25 weeks, reduce the completion time of the project by 5 weeks in the most economical way.
Activity |
Normal Time |
Normal |
Crash Time |
Crash |
Maximum |
Crash Cost |
---|---|---|---|---|---|---|
A |
3 | 550 | 2 | 930 | 1 | 380 |
B |
4 | 650 | 3 | 740 | 1 | 90 |
C |
6 | 800 | 3 | 1,310 | 3 | 170 |
D |
6 | 1,500 | 4 | 2,140 | 2 | 320 |
E |
6 | 1,750 | 4 | 2,250 | 2 | 250 |
F |
5 | 200 | 5 | 200 | 0 | 0 |
G |
7 | 1,400 | 5 | 1,690 | 2 | 145 |
H |
3 | 500 | 3 | 500 | 0 | 0 |
AON network diagram
(If there is no amount for a box enter 0. All boxes must be filled.)
Reduce A by ____________a number of weeks week(s), B by ———- a number of weeks week(s), C by ————— a number of weeks week(s), D by —————-a number of weeks week(s), E by ————— a number of weeks week(s), F by —————– a number of weeks week(s), G by ———— a number of weeks week(s), H by ————- a number of weeks week(s).
Total additional cost is $enter total additional cost in dollars